SF Prep Notes

CCEA approves three railway multitracking projects adding about 901 km across six states

On 5 May 2026 the Cabinet Committee on Economic Affairs approved three railway multitracking projects — Nagda–Mathura, Guntakal–Wadi and Burhwal–Sitapur 3rd and 4th lines — costing about ₹23,437 crore and adding about 901 km across 19 districts in six states.

Summary

Three railway multitracking projects costing about ₹23,437 crore were approved by the Cabinet Committee on Economic Affairs chaired by PM Narendra Modi on 5 May 2026: the 3rd and 4th lines on Nagda–Mathura, Guntakal–Wadi and Burhwal–Sitapur. Covering 19 districts in Madhya Pradesh, Rajasthan, Uttar Pradesh, Karnataka, Andhra Pradesh and Telangana, they will add about 901 km to the Indian Railways network, improve connectivity for about 4,161 villages with roughly 83 lakh people, and be completed by 2030–31. The projects are planned under the PM-Gati Shakti National Master Plan and will improve access to places such as Mahakaleshwar, Ranthambore, Kuno and Keoladeo National Parks, Mathura, Vrindavan and Naimisharanya.

Key facts

Approved
CCEA, 5 May 2026
Projects
Nagda–Mathura, Guntakal–Wadi, Burhwal–Sitapur 3rd & 4th lines
Cost
~₹23,437 crore; completion by 2030–31
Reach
~901 km; 19 districts in MP, Rajasthan, UP, Karnataka, AP, Telangana
Villages
~4,161 villages, ~83 lakh people; PM-Gati Shakti planning

Practice MCQs 2 questions

Q1

The three railway multitracking projects approved by the CCEA in May 2026 will add about how many kilometres to the Indian Railways network?

Show answer

Correct answer: D — 901 km

The three projects will increase the existing network of Indian Railways by about 901 km.

Q2 Advanced

Which of the following is one of the three railway multitracking projects approved by the CCEA on 5 May 2026?

Show answer

Correct answer: A — Nagda–Mathura 3rd and 4th line

The approved projects are the 3rd and 4th lines on Nagda–Mathura, Guntakal–Wadi and Burhwal–Sitapur.

← All current affairs