SF Prep Notes

CCEA approves three rail multitracking projects worth ₹18,509 crore: Kasara–Manmad, Delhi–Ambala and Ballari–Hosapete

The Cabinet Committee on Economic Affairs approved three railway multitracking projects worth about ₹18,509 crore across Delhi, Haryana, Maharashtra and Karnataka on 13 February 2026, adding about 389 km to the network.

Summary

The Cabinet Committee on Economic Affairs chaired by Prime Minister Narendra Modi approved three railway projects worth about ₹18,509 crore on 13 February 2026: 3rd and 4th lines on the Kasara–Manmad, Delhi–Ambala and Ballari–Hosapete sections. The projects cover 12 districts in Delhi, Haryana, Maharashtra and Karnataka and will add about 389 km to the Indian Railways network by 2030-31. They will connect about 3,902 villages with a population of about 97 lakh and carry an extra 96 million tonnes of freight a year. They will also improve access to places such as Trimbakeshwar and Hampi, a UNESCO World Heritage Site.

Key facts

Approved
13 February 2026 by CCEA (announced 14 February)
Projects
Kasara–Manmad, Delhi–Ambala, Ballari–Hosapete 3rd & 4th lines
Cost
About ₹18,509 crore
Network added
About 389 km; 12 districts in 4 states/UT
Completion
By 2030-31
Freight
Extra 96 MTPA

Practice MCQs 2 questions

Q1 Advanced

Which of the following rail sections was NOT among the three multitracking projects approved by the CCEA in February 2026?

Show answer

Correct answer: D — Sainthia–Pakur

The three projects were Kasara–Manmad, Delhi–Ambala and Ballari–Hosapete 3rd and 4th lines.

Q2

By about how many kilometres will the three multitracking projects approved on 13 February 2026 increase the Indian Railways network?

Show answer

Correct answer: C — 389 km

The three projects will add about 389 km across 12 districts.