SF Prep Notes

Cabinet approves ₹1,507-crore greenfield airport at Kota-Bundi, Rajasthan

The Cabinet Committee on Economic Affairs on 19 August 2025 approved the Airports Authority of India's proposal for a greenfield airport at Kota-Bundi, Rajasthan, at an estimated cost of ₹1,507 crore.

Summary

The Cabinet Committee on Economic Affairs approved on 19 August 2025 the Airports Authority of India (AAI) proposal to develop a greenfield airport at Kota-Bundi in Rajasthan at an estimated cost of ₹1,507 crore. The Rajasthan government has transferred 440.06 hectares of land to AAI for an airport suitable for A-321 type aircraft. The project includes a 20,000 sqm terminal building for 1,000 peak-hour passengers and an annual capacity of 2 million passengers, a 3,200 m x 45 m runway (11/29) and an apron with 7 parking bays. The existing AAI-owned Kota airport has only a 1,220 m runway (08/26) suited to Code 'B' aircraft and cannot be developed for commercial operations because of inadequate land and surrounding urbanisation.

Key facts

Approved
19 Aug 2025, CCEA
Developer
Airports Authority of India
Cost
₹1,507 crore
Land
440.06 ha transferred by Rajasthan govt
Aircraft
A-321 type
Terminal
20,000 sqm; 1,000 peak-hour pax; 2 MPPA
Runway
11/29, 3,200 m x 45 m; apron with 7 bays
Existing airport
Runway 08/26, 1,220 m x 38 m (Code B)

Practice MCQs 3 questions

Q1

The greenfield airport at Kota-Bundi approved by the Cabinet on 19 August 2025 is being designed to suit which type of aircraft?

Show answer

Correct answer: B — A-321

The Rajasthan government transferred 440.06 ha to AAI for a greenfield airport suitable for operation of A-321 type aircraft.

Q2 Advanced

How much land has the Rajasthan government transferred to the Airports Authority of India for the Kota-Bundi greenfield airport?

Show answer

Correct answer: A — 440.06 hectares

The Government of Rajasthan has transferred 440.06 hectares of land to AAI for development of the greenfield airport.

Q3 Advanced

Which runway specification is planned for the new Kota-Bundi greenfield airport?

Show answer

Correct answer: D — Runway 11/29, 3,200 m x 45 m

The project includes Runway 11/29 of 3,200 m x 45 m; Runway 08/26 of 1,220 m x 38 m belongs to the existing Kota airport.

← All current affairs