SF Prep Notes

Cabinet approves Rs 8,970 crore 4-lane Guwahati–Tezpur corridor on NH-15 in Assam

The Cabinet Committee on Economic Affairs on 6 August 2026 approved a 135.87 km, 4-lane access-controlled Guwahati–Tezpur corridor on NH-15 in Assam at a cost of Rs 8,970.20 crore.

Summary

The Cabinet Committee on Economic Affairs approved the 135.87 km, 4-lane access-controlled Guwahati–Tezpur corridor of NH-15 in Assam, from Baihata Chariali to Tezpur, on 6 August 2026. The project will be built in Build-Operate-Transfer (Toll) mode at a capital cost of Rs 8,970.20 crore. It includes a 4.9 km Emergency Landing Facility in the Tezpur bypass, planned with the Indian Air Force, five major bypasses and an elephant underpass. It is expected to double average travel speeds and halve travel time, decongesting NH-27 south of the Brahmaputra.

Key facts

Corridor
Guwahati (Baihata Chariali)–Tezpur, NH-15, Assam
Length
135.87 km, 4-lane access-controlled
Cost
Rs 8,970.20 crore
Mode
Build-Operate-Transfer (Toll)
Special features
4.9 km Emergency Landing Facility; elephant underpass
Approved by
CCEA, 6 Aug 2026

Practice MCQs 3 questions

Q1

The 4-lane Guwahati–Tezpur corridor approved by the CCEA in August 2026 is being developed along which National Highway?

Show answer

Correct answer: B — NH-15

The 135.87 km corridor from Baihata Chariali to Tezpur is on NH-15 in Assam.

Q2 Advanced

In which mode will the Guwahati–Tezpur corridor on NH-15 be developed?

Show answer

Correct answer: C — Build-Operate-Transfer (Toll)

The project will be developed on Build-Operate-Transfer (Toll) mode at a capital cost of Rs 8,970.20 crore.

Q3 Advanced

Consider the following statements about the Guwahati–Tezpur corridor approved in August 2026: 1. It includes an Emergency Landing Facility in the Tezpur bypass, finalised with the Indian Air Force. 2. The total project length is about 235 km. Which of the above is/are correct?

Show answer

Correct answer: A — 1 only

Only statement 1 is correct. The project length is 135.87 km; the 4.9 km Emergency Landing Facility is in the Tezpur bypass.

← All current affairs