Vaishnaw and Japan's Transport Minister Nakano visit Mumbai–Ahmedabad bullet train sites at Surat and BKC

On 3 October 2025, Railway Minister Ashwini Vaishnaw and Japan's Land, Infrastructure, Transport and Tourism Minister Hiromasa Nakano visited Mumbai–Ahmedabad High-Speed Rail sites at Surat and Mumbai's BKC.

Summary

On 3 October 2025, Railway Minister Ashwini Vaishnaw and Japan's Minister of Land, Infrastructure, Transport and Tourism, Hiromasa Nakano, visited sites of the Mumbai–Ahmedabad High-Speed Rail (bullet train) project. At Surat they watched the J-slab ballast-less track being installed on the viaduct. They then travelled to Mumbai by Vande Bharat Express and reviewed the underground Bandra Kurla Complex (BKC) station. Its excavation has passed 30 metres in depth with about 84% done, and it will have three levels with road and metro links. As of September 2025, 323 km of viaduct, 399 km of piers and 211 km of track bed were complete on the 508 km corridor. Seventeen river bridges, 5 PSC bridges and 9 steel bridges had also been finished. The Railways said the visit showed the strong India–Japan partnership on the country's first high-speed rail corridor.

Key facts

Corridor
Mumbai–Ahmedabad HSR, 508 km
Progress (Sep 2025)
323 km viaduct; 399 km piers; 211 km track bed; 17 river bridges
BKC station
Underground; 30 m+ deep; ~84% excavation; 3 levels
Japan
MLIT Minister Hiromasa Nakano

Practice MCQs 3 questions

Q1

What is the total length of the Mumbai–Ahmedabad High-Speed Rail (bullet train) corridor?

Show answer

Correct answer: B — 508 km

PIB (Ministry of Railways): the Mumbai–Ahmedabad Bullet Train corridor is 508 km long; by September 2025, 323 km of viaduct had been completed.

Q2 Advanced

Hiromasa Nakano, who visited the bullet train sites with Ashwini Vaishnaw on 3 October 2025, holds which portfolio in Japan?

Show answer

Correct answer: D — Minister of Land, Infrastructure, Transport and Tourism

PIB: Japan's Minister of Land, Infrastructure, Transport & Tourism, H.E. Hiromasa Nakano, visited the Surat and Mumbai HSR sites with Union Minister Ashwini Vaishnaw.

Q3 Advanced

Consider the following statements about the Mumbai–Ahmedabad HSR project (status as of September–October 2025): 1. 323 km of viaduct had been completed. 2. The Bandra Kurla Complex (BKC) station is being built as an elevated station. Which of the statements given above is/are correct?

Show answer

Correct answer: A — 1 only

Only 1 is correct. PIB: 323 km of viaduct had been completed by September 2025. The BKC station is an underground facility, with excavation over 30 metres deep and about 84% complete.