Tamil Nadu cabinet approves Battery Energy Storage Systems Policy 2026

On 29 October 2026, the Tamil Nadu cabinet approved the Battery Energy Storage Systems (BESS) Policy 2026, offering a 100% waiver of transmission and wheeling charges for eligible storage projects of 1 MW and above.

Summary

The Tamil Nadu cabinet approved the Tamil Nadu Battery Energy Storage Systems (BESS) Policy, 2026 on 29 October 2026 to speed up battery storage across generation and transmission networks, make better use of renewable energy and cut curtailment. It covers standalone BESS and BESS co-located with solar, wind or hybrid plants, of 1 MW and above. The policy envisages at least 2.5 GW/10 GWh of storage during its three-year validity, makes new solar and solar-hybrid projects of 1 MW and above install storage of at least 10% of capacity with four-hour discharge, and offers eligible projects a 100% waiver of transmission and wheeling charges for 10 years, subject to TNERC approval. It applies to projects applying on or after notification or commissioned on or after 1 April 2027.

Key facts

Policy
Tamil Nadu Battery Energy Storage Systems Policy, 2026
Approved
State cabinet, 29 October 2026
Capacity goal
At least 2.5 GW / 10 GWh
Validity
Three years from notification (or till 10 GWh commissioned)
Mandate
New solar/solar-hybrid 1 MW+: storage of at least 10% capacity, 4-hour discharge
Incentive
100% waiver of transmission and wheeling charges for 10 years (subject to TNERC)
Applies to
Applications after notification or projects commissioned from 1 April 2027

Practice MCQs 3 questions

Q1

Which State's cabinet approved a Battery Energy Storage Systems (BESS) Policy 2026 on 29 October 2026?

Show answer

Correct answer: C — Tamil Nadu

The Tamil Nadu cabinet approved the Tamil Nadu BESS Policy, 2026 on 29 October 2026.
Q2 Advanced

Under Tamil Nadu's BESS Policy 2026, eligible battery storage projects get what relief on transmission and wheeling charges?

Show answer

Correct answer: D — 100% waiver for 10 years

Eligible projects get a 100% waiver of transmission and wheeling charges for 10 years from commissioning, subject to TNERC approval.
Q3 Advanced

Consider the following about Tamil Nadu's BESS Policy 2026: 1. New solar and solar-hybrid projects of 1 MW and above must install storage equal to at least 10% of capacity with four-hour discharge. 2. It envisages at least 2.5 GW/10 GWh of battery storage during its validity. Which of the statements given above is/are correct?

Show answer

Correct answer: C — Both 1 and 2

Both are correct: the policy mandates 10% storage with four-hour discharge for new 1 MW+ solar/solar-hybrid projects and envisages at least 2.5 GW/10 GWh.