Sakleshpur–Subramanya Road ghat section electrified; Bengaluru–Mangaluru route now fully electric

South Western Railway completed electrification of the 55-km Sakleshpur–Subramanya Road ghat section in Karnataka with a successful electric locomotive trial on 28 December 2025, making the whole Bengaluru–Mangaluru route electrified.

Summary

The Sakleshpur–Subramanya Road ghat section in Karnataka, one of the toughest stretches on Indian Railways, was declared fully electrified after a successful electric locomotive trial on 28 December 2025 by the Mysuru Division of South Western Railway. The 55-km section has a ruling gradient of 1 in 50, 57 tunnels and 108 sharp curves in landslide-prone Western Ghats terrain; work began in December 2023 and cost ₹93.55 crore. With this, the entire Bengaluru–Mangaluru rail route is electrified, and Railway Minister Ashwini Vaishnaw said Vande Bharat trains can now run to Mangaluru.

Key facts

Trial
Electric loco trial, 28 December 2025
Section
Sakleshpur–Subramanya Road, 55 km (Karnataka)
Terrain
1 in 50 gradient; 57 tunnels; 108 sharp curves
Work
Began December 2023; five switching stations; ₹93.55 crore
Result
Entire Bengaluru–Mangaluru route electrified

Practice MCQs 3 questions

Q1

With the electrification of the Sakleshpur–Subramanya Road ghat section in December 2025, which rail route became fully electrified?

Show answer

Correct answer: B — Bengaluru–Mangaluru

PIB (Railways): with this ghat stretch electrified, the entire Bengaluru–Mangaluru rail route is now fully electrified.

Q2 Advanced

What is the length of the Sakleshpur–Subramanya Road ghat section electrified in December 2025?

Show answer

Correct answer: C — 55 km

PIB, The Hindu and The New Indian Express: the electrified ghat section covers 55 km between Sakleshpur and Subramanya Road.

Q3 Advanced

Consider the following statements about the Sakleshpur–Subramanya Road ghat section: 1. The section has a steep ruling gradient of 1 in 50. 2. The section passes through 57 tunnels. 3. Electrification work on the section began in December 2023. Which of the statements given above is/are correct?

Show answer

Correct answer: D — 1, 2 and 3

PIB, The Hindu and The New Indian Express: the section has a 1-in-50 ruling gradient and 57 tunnels, and work began in December 2023. All three statements are correct.