NMDC commissions 2 MTPA pellet plant at Nagarnar as part of ₹5,427 crore iron ore project in Bastar

On 27 September 2026 NMDC Ltd commissioned its 2 MTPA pellet plant at Nagarnar, Chhattisgarh, part of a ₹5,427 crore project linking its Bacheli iron ore operations with its Nagarnar steel plant.

Summary

The integrated project includes a new iron ore processing plant at Bacheli, a 135 km, 15 MTPA slurry pipeline carrying iron ore concentrate from Bacheli to Nagarnar instead of by road, and the pellet plant, which uses Straight Grate Induration technology. It lets NMDC turn iron ore fines and slimes from its Bailadila mines into concentrate and pellets. Chairman and Managing Director Amitava Mukherjee monitored the first production live from headquarters.

Key facts

Company
NMDC Ltd
Project cost
₹5,427 crore
Pellet plant
2 MTPA, Nagarnar, Chhattisgarh
Slurry pipeline
135 km, 15 MTPA, Bacheli to Nagarnar
Technology
Straight Grate Induration
Raw material
Fines and slimes from Bailadila mines
CMD
Amitava Mukherjee

Practice MCQs 3 questions

Q1 Advanced

NMDC's 2 MTPA pellet plant commissioned in September 2026 is located at which place in Chhattisgarh?

Show answer

Correct answer: B — Nagarnar

The pellet plant is at Nagarnar, Bastar, linked by a 135 km slurry pipeline to Bacheli.

Q2 Advanced

How long is the slurry pipeline in NMDC's ₹5,427 crore project, carrying iron ore concentrate from Bacheli to Nagarnar?

Show answer

Correct answer: C — 135 km

The 135 km, 15 MTPA slurry pipeline carries concentrate from Bacheli to Nagarnar instead of by road.

Q3 Advanced

Consider the following statements about the NMDC project commissioned in 2026: 1. The pellet plant uses Straight Grate Induration technology. 2. It processes fines and slimes from the Bailadila mines. Which of the above is/are correct?

Show answer

Correct answer: C — Both 1 and 2

Both are correct as per the Ministry of Steel release.

← All current affairs