NHAI awards HAM contracts for 111-km six-lane Capital Region Ring Road around Bhubaneswar

NHAI issued Letters of Award on 3 March 2026 for the 111-km six-lane access-controlled Capital Region Ring Road (Bhubaneswar Bypass) in Odisha, from Rameshwar to Tangi, in three packages under the Hybrid Annuity Mode.

Summary

The National Highways Authority of India (NHAI) issued Letters of Award, announced on 3 March 2026, for the six-lane access-controlled greenfield Capital Region Ring Road (Bhubaneswar Bypass) in Odisha. The 111-km road from Rameshwar to Tangi will be built in three packages under the Hybrid Annuity Mode (HAM) and is expected to be completed in about 30 months. Package I (Rameshwar–Bilipada, 40 km) went to Patel Infrastructure, Package II (Bilipada–Gobindpur, 30 km) to VRC Constructions, and Package III (Gobindpur–Tangi near Bandola Toll Plaza, 40 km) to HG Infra Engineering. With a design speed of 100 kmph, the corridor is meant to decongest Bhubaneswar, Cuttack and Khordha.

Key facts

Date
3 March 2026 (LOAs announced)
Project
Capital Region Ring Road (Bhubaneswar Bypass), Odisha
Length
111 km, six-lane, access-controlled, greenfield
Route
Rameshwar to Tangi
Mode
Hybrid Annuity Mode (HAM), 3 packages
Timeline
About 30 months
Design speed
100 kmph

Practice MCQs 3 questions

Q1

The Capital Region Ring Road project, for which NHAI issued Letters of Award in March 2026, is being built around which city?

Show answer

Correct answer: B — Bhubaneswar

The 111-km Capital Region Ring Road is also called the Bhubaneswar Bypass, in Odisha.

Q2 Advanced

Under which model will the Bhubaneswar Capital Region Ring Road be built?

Show answer

Correct answer: C — Hybrid Annuity Mode

The 111-km road will be built in three packages under the Hybrid Annuity Mode (HAM).

Q3 Advanced

Consider the following statements about the Capital Region Ring Road (Bhubaneswar Bypass): 1. It runs for 111 km from Rameshwar to Tangi. 2. It is a four-lane brownfield upgrade of an existing highway. Which of the above is/are correct?

Show answer

Correct answer: A — 1 only

Only statement 1 is correct. The project is a six-lane access-controlled greenfield road with a design speed of 100 kmph.