SF Prep Notes

Manohar Lal launches National Electricity Plan (Transmission) to evacuate 500 GW RE by 2030

On 14 October 2024, in New Delhi, Power Minister Manohar Lal launched the National Electricity Plan (Transmission) prepared by the CEA, at a CEA brainstorming conclave (14-15 October).

Summary

On 14 October 2024, in New Delhi, Union Minister for Power Manohar Lal launched the National Electricity Plan (Transmission), prepared by the Central Electricity Authority (CEA), during a two-day CEA brainstorming conclave (14-15 October 2024). The plan aims to transmit 500 GW of renewable energy capacity by 2030 and over 600 GW by 2032. It adds over 1,91,000 ckm of transmission lines and 1,270 GVA of transformation capacity (220 kV and above) during 2022-23 to 2031-32, plus 33 GW of HVDC bi-pole links. Inter-regional capacity is to rise from 119 GW to 143 GW by 2027 and 168 GW by 2032. It considers 47 GW of battery storage and 31 GW of pumped storage, and shows an investment opportunity of over ₹9,15,000 crore till 2032.

Key facts

Launched
14 Oct 2024, New Delhi, by Manohar Lal
Prepared by
CEA
RE to transmit
500 GW by 2030; 600+ GW by 2032
Lines
1,91,000+ ckm (2022-23 to 2031-32)
Transformation
1,270 GVA
Inter-regional capacity
119 GW to 143 GW (2027), 168 GW (2032)
Investment
₹9,15,000+ crore till 2032

Practice MCQs 3 questions

Q1

The National Electricity Plan (Transmission) launched on 14 October 2024 was prepared by:

Show answer

Correct answer: C — Central Electricity Authority

PIB (14 Oct 2024): CEA prepared the detailed National Electricity Plan (Transmission) in consultation with stakeholders.

Q2 Advanced

As per the National Electricity Plan (Transmission), the investment opportunity in the transmission sector till 2032 is over:

Show answer

Correct answer: B — ₹9,15,000 crore

PIB (14 Oct 2024): the plan provides visibility of an investment opportunity of over INR 9,15,000 Crores in the transmission sector till 2032.

Q3 Advanced

Consider the following statements about the National Electricity Plan (Transmission): 1. It considers 47 GW of Battery Energy Storage Systems and 31 GW of Pumped Storage Plants. 2. Inter-regional transmission capacity is planned to reach 168 GW by 2032. Which of the statements given above is/are correct?

Show answer

Correct answer: C — Both 1 and 2

Both correct per PIB (14 Oct 2024): the plan considers 47 GW BESS and 31 GW PSP; inter-regional capacity to increase to 143 GW by 2027 and 168 GW by 2032 from 119 GW.

← All current affairs