MNRE amends ALMM order for solar PV cells; 1 June 2026 date unchanged

On 28 July 2025, MNRE amended the ALMM order for solar PV cells so that the mandate applies only one month after the ALMM list for cells is published.

Summary

The Ministry of New and Renewable Energy (MNRE) issued an amendment on 28 July 2025 to its order of 9 December 2024 on the Approved List of Models and Manufacturers (ALMM) for solar PV cells. Under the amendment, ALMM for solar PV cells becomes mandatory only one month after the cells list is published, which is under process, easing procedures for projects bid out by government agencies, including under Section 63 of the Electricity Act, 2003. The requirement for projects commissioned from 1 June 2026 stays unchanged. ALMM for solar PV modules has applied since 10 April 2021. Domestic manufacturing capacity stands at 91 GW of modules and 27 GW of cells.

Key facts

Amendment issued
28 July 2025
Original cells order
9 December 2024
New rule
Mandatory one month after ALMM cells list is published
Cells mandate date
1 June 2026 (unchanged)
ALMM for modules
Since 10 April 2021
Capacity
91 GW modules, 27 GW cells

Practice MCQs 2 questions

Q1 Advanced

Under MNRE's amendment of 28 July 2025, the ALMM requirement for solar PV cells becomes mandatory:

Show answer

Correct answer: C — One month after the ALMM list for solar PV cells is published

PIB (28 July 2025): ALMM for solar PV cells will be mandatory only one month after publication of the ALMM list for cells; the 1 June 2026 date for commissioned projects is unchanged.

Q2

As per MNRE (July 2025), India's domestic solar manufacturing capacity stands at:

Show answer

Correct answer: B — 91 GW modules and 27 GW cells

PIB: domestic solar manufacturing currently stands at 91 GW of solar PV modules and 27 GW of solar PV cells.