CEA concurs record six pumped storage project DPRs of about 7.5 GW in 2024-25

The Central Electricity Authority concurred Detailed Project Reports of six hydro pumped storage projects with about 7.5 GW capacity in 2024-25, a record, and aims to concur at least 13 projects of about 22 GW in 2025-26.

Summary

The Central Electricity Authority (CEA) concurred Detailed Project Reports (DPRs) of a record six hydro pumped storage projects (PSPs) with a combined capacity of about 7.5 GW during 2024-25, the Ministry of Power said on 12 April 2025. They are Upper Indravati (600 MW, Odisha), Sharavathy (2,000 MW, Karnataka), Bhivpuri (1,000 MW, Maharashtra), Bhavali (1,500 MW, Maharashtra), MP-30 (1,920 MW, Madhya Pradesh) and Chitravathi (500 MW, Andhra Pradesh). For 2025-26, CEA targets concurrence of at least 13 PSPs of about 22 GW. India's pumped storage potential is estimated at over 200 GW. DPRs are submitted through the 'Jalvi Store' portal and appraised with the Central Water Commission (CWC), Geological Survey of India (GSI) and Central Soil and Materials Research Station (CSMRS).

Key facts

2024-25 concurrence
6 PSPs, about 7.5 GW (record)
Largest
Sharavathy, 2,000 MW (Karnataka)
Others
Upper Indravati 600 MW (OD), Bhivpuri 1,000 MW (MH), Bhavali 1,500 MW (MH), MP-30 1,920 MW (MP), Chitravathi 500 MW (AP)
2025-26 target
at least 13 PSPs, about 22 GW
Estimated potential
over 200 GW
Portal
Jalvi Store

Practice MCQs 3 questions

Q1

How many hydro pumped storage project DPRs did the Central Electricity Authority concur in 2024-25, a record?

Show answer

Correct answer: B — Six

Six projects with a combined capacity of about 7.5 GW; thirteen is the target for 2025-26.

Q2 Advanced

Which was the largest pumped storage project among those whose DPRs CEA concurred in 2024-25?

Show answer

Correct answer: C — Sharavathy, Karnataka

Sharavathy, Karnataka, at 2,000 MW; MP-30 is 1,920 MW and Bhavali 1,500 MW.

Q3 Advanced

Consider the following statements about pumped storage projects (PSPs) in India, as stated by the Ministry of Power in April 2025: 1. CEA aims to concur at least 13 PSPs of about 22 GW in 2025-26. 2. India's estimated pumped storage potential is below 100 GW. Which of the statements given above is/are correct?

Show answer

Correct answer: A — 1 only

Only 1 is correct. The 2025-26 target is at least 13 PSPs of about 22 GW; the estimated potential is over 200 GW.