On 24 October 2024, in India, the Cabinet Committee on Economic Affairs approved two railway projects worth about ₹6,798 crore: doubling of 256 km in north Bihar and a 57 km new line between Errupalem and Namburu via Amaravati.
Summary
On 24 October 2024, in India, the Cabinet Committee on Economic Affairs chaired by PM Narendra Modi approved two railway projects with a total estimated cost of about ₹6,798 crore, to be completed in five years. They are the doubling of the Narkatiaganj-Raxaul-Sitamarhi-Darbhanga and Sitamarhi-Muzaffarpur section (256 km) and a new 57 km line between Errupalem and Namburu via Amaravati. Covering 8 districts in Andhra Pradesh, Telangana and Bihar, they will add about 313 km to the network. The new line will give direct connectivity to Amaravati, the proposed capital of Andhra Pradesh, and the doubling will serve two Aspirational Districts, Sitamarhi and Muzaffarpur.
Key facts
- Date
- 24 Oct 2024
- Approved by
- CCEA
- Total cost
- About ₹6,798 crore
- Doubling
- Narkatiaganj-Raxaul-Sitamarhi-Darbhanga & Sitamarhi-Muzaffarpur, 256 km
- New line
- Errupalem-Namburu via Amaravati, 57 km
- States
- Andhra Pradesh, Telangana, Bihar (8 districts)
- Network addition
- About 313 km
- Completion
- 5 years
- Aspirational districts
- Sitamarhi, Muzaffarpur
Practice MCQs 4 questions
What is the total estimated cost of the two railway projects approved by the CCEA on 24 October 2024?
Show answer
Correct answer: C — About ₹6,798 crore
PIB, 24 Oct 2024: CCEA approved two railway projects with total estimated cost of Rs.6,798 crore (approx.).
The new railway line approved on 24 October 2024 to provide direct connectivity to Amaravati runs between:
Show answer
Correct answer: A — Errupalem and Namburu
PIB, 24 Oct 2024: construction of new line between Errupalem and Namburu via Amaravati covering 57 kms.
Consider the following about the railway projects approved on 24 October 2024: 1. Together they cover 8 districts in Andhra Pradesh, Telangana and Bihar. 2. The doubling project in north Bihar covers 157 km. Which of the statements given above is/are correct?
Show answer
Correct answer: A — 1 only
PIB, 24 Oct 2024: the two projects cover 8 districts in 3 states — Andhra Pradesh, Telangana and Bihar (1 is correct). The Narkatiaganj-Raxaul-Sitamarhi-Darbhanga & Sitamarhi-Muzaffarpur doubling covers 256 km, not 157 km (2 is wrong).
Which two Aspirational Districts will be served by the north Bihar doubling project approved on 24 October 2024?
Show answer
Correct answer: D — Sitamarhi and Muzaffarpur
PIB, 24 Oct 2024: the multi-tracking project will enhance connectivity to two Aspirational Districts (Sitamarhi and Muzaffarpur).