CCEA approves ₹6,969-crore 4-lane access-controlled NH-927 from Barabanki to Bahraich in UP

The Cabinet Committee on Economic Affairs on 18 March 2026 approved a 101.515-km 4-lane access-controlled NH-927 from Barabanki to Bahraich in Uttar Pradesh on Hybrid Annuity Mode at a cost of ₹6,969.04 crore.

Summary

The Barabanki–Bahraich section of NH-927 in Uttar Pradesh will be built as a 101.515-km 4-lane access-controlled highway on Hybrid Annuity Mode at a capital cost of ₹6,969.04 crore, under a decision of the Cabinet Committee on Economic Affairs on 18 March 2026. The stretch is part of the Lucknow–Rupaidiha corridor, has 48.28 km of bypasses and will cut travel time to about one hour. The highway will improve access to Rupaidiha Land Port and create a cross-border trade corridor with Nepal via the Nepalganj border, also serving Shravasti and Lucknow airports.

Key facts

Approved
CCEA, 18 March 2026
Stretch
Barabanki–Bahraich, NH-927, 101.515 km
Cost / mode
₹6,969.04 crore; Hybrid Annuity Mode
Corridor
Lucknow–Rupaidiha; 48.28 km bypasses
Strategic link
Rupaidiha Land Port; Nepal via Nepalganj border
Jobs
36.54 lakh direct and 43.04 lakh indirect person-days

Practice MCQs 2 questions

Q1 Advanced

The Barabanki–Bahraich section of NH-927, approved by CCEA in March 2026, will be built on which mode?

Show answer

Correct answer: B — Hybrid Annuity Mode

The 101.515-km 4-lane access-controlled highway will be built on Hybrid Annuity Mode (HAM) at ₹6,969.04 crore.

Q2 Advanced

The upgraded Barabanki–Bahraich NH-927 corridor will improve access to which land port on the India–Nepal border?

Show answer

Correct answer: D — Rupaidiha

The project will establish a cross-border trade corridor with Nepal via the Nepalganj border, improving access to Rupaidiha Land Port.